United States βΊ Grid βΊ Interconnection queues βΊ Wyoming
SOLAR + STORAGE Β· WESTSolar + storage project 21-08241, Laramie County
Solar + storage project 21-08241, Laramie County is a 150 MW solar + storage request withdrawn in the West interconnection queue, in Laramie County, Wyoming, connecting to Platte River Power Authority.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21-08241
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Platte River Power Authority
- Connection point (POI)
- Rawhide-Roundhouse 230kV
- Location
- Laramie County, Wyoming
- Technology
- Solar: 150 MW Β· Battery
- Total requested
- 150 MW
- Queue status
- Withdrawn
- Entered queue
- 24 August 2021
- Proposed online date
- December 2025
Location
Marker shows the centre of Laramie County; the queue data does not give exact sites.
Other requests in Laramie County
- Solar + storage project CLPT G21, Laramie CountySolar + storage Β· 400 MW Β· agreement signed
- Onshore wind project GI-TC-2024-16, Laramie CountyOnshore wind Β· 400 MW Β· agreement signed
- Solar + storage project CLPT G20, Laramie CountySolar + storage Β· 365 MW Β· agreement signed
- Other project CLPT G17, Laramie CountyOther Β· 300 MW Β· agreement signed
- Onshore wind project GI-TC-2024-15, Laramie CountyOnshore wind Β· 250 MW Β· agreement signed
- Onshore wind project CLPT G24, Laramie CountyOnshore wind Β· 200 MW Β· agreement signed
- Onshore wind project CLPT G23, Laramie CountyOnshore wind Β· 150 MW Β· agreement signed
- Gas project CLPT G22, Laramie CountyGas Β· 115 MW Β· agreement signed
- Gas project 37316, Laramie CountyGas Β· 600 MW Β· in study
- Onshore wind project 21-08242, Laramie CountyOnshore wind Β· 350 MW Β· in study
- Wind + storage project GI-CS-2025-04, Laramie CountyWind + storage Β· 330 MW Β· in study
- Wind + storage project 39873, Laramie CountyWind + storage Β· 198 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem