United States βΊ Grid βΊ Interconnection queues βΊ Vermont
OTHER Β· ISO-NEDiesel
Diesel is a 9.1 MW other request withdrawn in the ISO-NE interconnection queue, in Essex County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2009 (completed)
- Withdrawn / abandonedMay 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 307
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- NGRID 34.5 kV Moore/Gilman Line
- Location
- Essex County, Vermont
- Technology
- Oil: 9.1 MW
- Total requested
- 9.1 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 July 2009
- Proposed online date
- May 2013
- Withdrawn
- May 2012
Location
Marker shows the centre of Essex County; the queue data does not give exact sites.
Other requests in Essex County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem