United States › Grid › Interconnection queues › South Dakota

SOLAR · WEST

Solar project BHBE G14, Custer County

Solar project BHBE G14, Custer County is a 80.0 MW solar request built and operating in the West interconnection queue, in Custer County, South Dakota, connecting to Black Hills Power.

Queue statusOperating
  1. PlanningQueued Apr 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
BHBE G14
Grid region
West (non-ISO utilities)
Utility / transmission owner
Black Hills Power
Developer
Energy of Utah
Connection point (POI)
West Hill - Stegall Tap
Location
Custer County, South Dakota
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
In-service
Queue status
Operational
Entered queue
2 April 2018
Proposed online date
December 2022

Location

Marker shows the centre of Custer County; the queue data does not give exact sites.

Power plants in South Dakota · Transmission lines in South Dakota

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem