United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

ONSHORE WIND Β· PJM

Onshore wind project T100, Bradford County

Onshore wind project T100, Bradford County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Bradford County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2007 (completed)
  2. Withdrawn / abandonedOct 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
T100
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Grover-East Towanda 230 kV
Location
Bradford County, Pennsylvania
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
12 November 2007
Proposed online date
September 2009
Withdrawn
October 2008

Location

Marker shows the centre of Bradford County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Bradford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem