Other project 84 is a 875 MW other request built and operating in the Southeast interconnection queue, connecting to Tennessee Valley Authority.
Request details
- Queue ID
- 84
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Technology
- Other: 875 MW
- Total requested
- 875 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 7 March 2000
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Solar project 522, Choctaw CountySolar Β· 67.0 MW Β· in study
- Other project 84, Choctaw CountyOther Β· 875 MW Β· built
- Other project 70, Choctaw CountyOther Β· 815 MW Β· built
- Other project 70Other Β· 815 MW Β· built
- Other project , Choctaw CountyOther Β· 480 MW Β· built
- Other project Other Β· 480 MW Β· built
- Other project 50, Choctaw CountyOther Β· 800 MW Β· withdrawn
- Onshore wind project J2698, Choctaw CountyOnshore wind Β· 500 MW Β· withdrawn
- Other project J2692, Choctaw CountyOther Β· 500 MW Β· withdrawn
- Onshore wind project J2591, Choctaw CountyOnshore wind Β· 500 MW Β· withdrawn
- Solar + storage project 472, Choctaw CountySolar + storage Β· 300 MW Β· withdrawn
- Solar + storage project 508, Choctaw CountySolar + storage Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem