🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Realitos Solar SLF

Realitos Solar SLF is a 151 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Duval County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0196
Grid region
ERCOT (Texas)
Developer
Mesquite Creek LLC
Connection point (POI)
Bruni (#8297) – Crestonio (#8695) 138 kV line; AEP
Location
Duval County, Texas
Technology
Solar: 151 MW · Battery
Total requested
151 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
7 September 2023
Proposed online date
December 2028

Location

Marker shows the centre of Duval County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Duval County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem