πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

ONSHORE WIND Β· PJM

Onshore wind project R92, Clearfield County

Onshore wind project R92, Clearfield County is a 70.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Clearfield County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandonedDec 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R92
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
DuBois 115kV
Location
Clearfield County, Pennsylvania
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
31 January 2007
Proposed online date
June 2009
Withdrawn
December 2013

Location

Marker shows the centre of Clearfield County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Clearfield County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem