United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
SOLAR Β· MISOSolar project J801, Pierce County
Solar project J801, Pierce County is a 74.0 MW solar request withdrawn in the MISO interconnection queue, in Pierce County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJul 2024 (project stopped here)
- ConsentedMay 2021 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J801
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DAIRYLAND POWER COOPERATIVE
- Connection point (POI)
- Crystal Cave-Rock Elm 161kV line tap
- Location
- Pierce County, Wisconsin
- Technology
- Solar: 74.0 MW
- Total requested
- 74.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Agreement signed
- 19 May 2021
- Proposed online date
- November 2023
- Withdrawn
- July 2024
Location
Marker shows the centre of Pierce County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Pierce County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem