Solar + storage project Q329, Pinal County

Solar + storage project Q329, Pinal County is a 75.0 MW solar + storage request withdrawn in the West interconnection queue, in Pinal County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q329
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Milligan - Casa Grande 230kV Line
Location
Pinal County, Arizona
Technology
Solar: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
20 March 2020
Proposed online date
June 2022

Location

Marker shows the centre of Pinal County; the queue data does not give exact sites.