🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Pirate BESS

Pirate BESS is a 9.8 MW battery storage request built and operating in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0597
Grid region
ERCOT (Texas)
Location
San Patricio County, Texas
Technology
Battery: 9.8 MW
Total requested
9.8 MW
Study phase
IA Executed
Queue status
Operational
Came online
January 2025

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem