United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

ONSHORE WIND Β· SPP

Onshore wind project GEN-2008-009, Chaves County

Onshore wind project GEN-2008-009, Chaves County is a 60.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Chaves County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2008 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2008-009
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
San Juan Tap 230kV
Location
Chaves County, New Mexico
Technology
Wind: 60.0 MW
Total requested
60.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
18 February 2008
Proposed online date
March 2012
Withdrawn
June 2011

Location

Marker shows the centre of Chaves County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Chaves County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem