United States βΊ Grid βΊ Interconnection queues βΊ Oregon
SOLAR Β· WESTSolar project 696, Polk County
Solar project 696, Polk County is a 2.2 MW solar request withdrawn in the West interconnection queue, in Polk County, Oregon, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2015 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 696
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Circuit 4M22, Rickreal, out of Independence substation
- Location
- Polk County, Oregon
- Technology
- Solar: 2.2 MW
- Total requested
- 2.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- WITHDRAWN BY CUSTOMER
- Queue status
- Withdrawn
- Entered queue
- 11 August 2015
- Proposed online date
- March 2017
Location
Marker shows the centre of Polk County; the queue data does not give exact sites.
Other requests in Polk County
- Other project G0970, Polk CountyOther Β· 160 MW Β· in study
- Battery storage project 24-242, Polk CountyBattery storage Β· 50.0 MW Β· in study
- Onshore wind project 12-053, Polk CountyOnshore wind Β· 87.5 MW Β· suspended
- Other project 99, Polk CountyOther Β· 0.8 MW Β· built
- Onshore wind project G0438, Polk CountyOnshore wind Β· 125 MW Β· withdrawn
- Other project 354, Polk CountyOther Β· 32.5 MW Β· withdrawn
- Solar project G1084, Polk CountySolar Β· 20.0 MW Β· withdrawn
- Solar project 984, Polk CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 1098, Polk CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 1097, Polk CountySolar Β· 3.0 MW Β· withdrawn
- Other project 386, Polk CountyOther Β· 1.6 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem