🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Mexico

SOLAR · WEST

Solar project SGI-PNM-2012-02, Valencia County

Solar project SGI-PNM-2012-02, Valencia County is a 9.0 MW solar request built and operating in the West interconnection queue, in Valencia County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. ConsentedDec 2012 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2012-02
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM-GDP Manzano College Feeder 12
Location
Valencia County, New Mexico
Technology
Solar: 9.0 MW
Total requested
9.0 MW
Service type
Network resource (NRIS)
Study phase
SGIA executed 12/3/2012.
Queue status
Operational
Entered queue
9 April 2012
Agreement signed
3 December 2012

Location

Marker shows the centre of Valencia County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Valencia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem