United States › Grid › Interconnection queues › New York
SOLAR + STORAGE · NYISOCrown Point Solar
Crown Point Solar is a 20.0 MW solar + storage request withdrawn in the NYISO interconnection queue, in Essex County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1661
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Crown Point Solar LLC
- Connection point (POI)
- 115kV Line #2 between Ticonderoga substation and Republic substation
- Location
- Essex County, New York
- Technology
- Solar: 20.0 MW · Battery
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 28 December 2023
Location
Marker shows the centre of Essex County; the queue data does not give exact sites.
Other requests in Essex County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem