United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTEstonian Solar
Estonian Solar is a 102 MW solar request withdrawn in the ERCOT interconnection queue, in Delta County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2019 (completed)
- Withdrawn / abandonedJun 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0340
- Grid region
- ERCOT (Texas)
- Developer
- 249RD 8ME
- Connection point (POI)
- 6834 Enloe Sw 138kV
- Location
- Delta County, Texas
- Technology
- Solar: 102 MW
- Total requested
- 102 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 6 May 2019
- Proposed online date
- December 2022
- Withdrawn
- June 2020
Location
Marker shows the centre of Delta County; the queue data does not give exact sites.
Other requests in Delta County
- Eagle Springs SolarSolar + storage Β· 77.2 MW Β· agreement signed
- Eagle Springs StorageSolar + storage Β· 33.1 MW Β· agreement signed
- Serengeti SolarSolar Β· 76.2 MW Β· in study
- Estonian StorageOther Β· 103 MW Β· suspended
- Estonian SolarSolar Β· 203 MW Β· built
- Estonian StorageOther Β· 102 MW Β· built
- Estonian 2 SolarSolar Β· 102 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem