πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

SOLAR Β· SPP

Solar project GEN-2024-075, Woodward County

Solar project GEN-2024-075, Woodward County is a 300 MW solar request withdrawn in the SPP interconnection queue, in Woodward County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2024 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-075
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Woodward 345 kV Substation
Location
Woodward County, Oklahoma
Technology
Solar: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 October 2024
Proposed online date
December 2029
Withdrawn
November 2025

Location

Marker shows the centre of Woodward County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Woodward County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem