Solar + storage project IA-PNM-2019-04, Valencia County

Solar + storage project IA-PNM-2019-04, Valencia County is a 51.0 MW solar + storage request withdrawn in the West interconnection queue, in Valencia County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2019-04
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Belen 115 kV Sub
Location
Valencia County, New Mexico
Technology
Solar: 51.0 MW Β· Battery
Total requested
51.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
23 April 2019
Proposed online date
June 2022

Location

Marker shows the centre of Valencia County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Valencia County