πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

ONSHORE WIND Β· PJM

Onshore wind project U2-055, Centre County

Onshore wind project U2-055, Centre County is a 89.1 MW onshore wind request withdrawn in the PJM interconnection queue, in Centre County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedAug 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
U2-055
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Karthaus-Milesburg 230kV
Location
Centre County, Pennsylvania
Technology
Wind: 89.1 MW
Total requested
89.1 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
27 June 2008
Proposed online date
July 2012
Withdrawn
August 2013

Location

Marker shows the centre of Centre County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Centre County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem