πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

SOLAR Β· PJM

Solar project AE1-057, Culpeper County

Solar project AE1-057, Culpeper County is a 5.0 MW solar request withdrawn in the PJM interconnection queue, in Culpeper County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2018 (completed)
  2. Withdrawn / abandonedNov 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-057
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Brandy DP 115 kV
Location
Culpeper County, Virginia
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
26 July 2018
Proposed online date
December 2019
Withdrawn
November 2018

Location

Marker shows the centre of Culpeper County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Culpeper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem