Solar + storage project AF1-312, Rockingham County

Solar + storage project AF1-312, Rockingham County is a 150 MW solar + storage request withdrawn in the PJM interconnection queue, in Rockingham County, North Carolina, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-312
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Dan River-Ridgeway 138 kV
Location
Rockingham County, North Carolina
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 September 2019
Proposed online date
December 2023
Withdrawn
October 2019

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.

Power plants in North Carolina Β· Transmission lines in North Carolina

Other requests in Rockingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem