United States › Grid › Interconnection queues › New Mexico

SOLAR · WEST

Solar project SGI-PNM-2010-11, San Miguel County

Solar project SGI-PNM-2010-11, San Miguel County is a 10.0 MW solar request built and operating in the West interconnection queue, in San Miguel County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued Jun 2010 (completed)
  2. ConsentedJul 2018 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2010-11
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM-RGD Gallinas Feeder 12
Location
San Miguel County, New Mexico
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
First Revised SGIA executed 7/20/18
Queue status
Operational
Entered queue
17 June 2010
Agreement signed
20 July 2018

Location

Marker shows the centre of San Miguel County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in San Miguel County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem