United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
ONSHORE WIND Β· WESTOnshore wind project IA-PNM-2007-08, San Miguel /Torrance Cty County
Onshore wind project IA-PNM-2007-08, San Miguel /Torrance Cty County is a 300 MW onshore wind request withdrawn in the West interconnection queue, in San Miguel /Torrance Cty County, New Mexico, connecting to Public Service Company of New Mexico.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2007 (completed)
- Withdrawn / abandonedJul 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IA-PNM-2007-08
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- El Cabo
- Location
- San Miguel /Torrance Cty County, New Mexico
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Energy only (ERIS)
- Study phase
- LGIA terminated by PNM 7/31/2015.
- Queue status
- Withdrawn
- Entered queue
- 22 May 2007
- Proposed online date
- September 2013
- Withdrawn
- July 2015
Location
Marker shows the centre of San Miguel /Torrance Cty County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico
Other requests in San Miguel /Torrance Cty County
- Solar project SGI-PNM-2017-06, San Miguel CountySolar Β· 10.0 MW Β· built
- Solar project SGI-PNM-2010-11, San Miguel CountySolar Β· 10.0 MW Β· built
- Solar project SGI-PNM-2015-03, San Miguel CountySolar Β· 10.0 MW Β· built
- Onshore wind project IA-PNM-2007-04, San Miguel Cty CountyOnshore wind Β· 70.0 MW Β· withdrawn
- Solar project SGI-PNM-2021-43, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2021-68, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2022-30, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2021-17, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2022-01, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2021-67, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2008-03, San Miguel CountySolar Β· 5.0 MW Β· withdrawn
- Solar project SGI-PNM-2022-13, San Miguel CountySolar Β· 1.7 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem