Solar project 316, Clay County

Solar project 316, Clay County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Clay County, Florida, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Aug 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
316
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Springbank-Seminole Plant (SEC) 230kV
Location
Clay County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
9 August 2017
Proposed online date
January 2024
Came online
January 2024

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Clay County