Solar project IC-869, Polk County

Solar project IC-869, Polk County is a 200 MW solar request withdrawn in the Southeast interconnection queue, in Polk County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2020 (completed)
  2. Withdrawn / abandonedJan 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-869
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bremen - Sewell Creek 230 kV Line
Location
Polk County, Georgia
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
28 May 2020
Proposed online date
April 2024
Withdrawn
January 2024

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.