🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wyoming

ONSHORE WIND · WEST

Onshore wind project 306-A, Converse County

Onshore wind project 306-A, Converse County is a 40.0 MW onshore wind request built and operating in the West interconnection queue, in Converse County, Wyoming, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Dec 2009 (completed)
  2. ConsentedDec 2011 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
306-A
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Pioneer Wind Park I, LLC
Connection point (POI)
Amassa substation, (DJ - Difficulty)
Location
Converse County, Wyoming
Technology
Wind: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed 12/12/11
Queue status
Operational
Entered queue
3 December 2009
Agreement signed
12 December 2011
Proposed online date
October 2016

Location

Marker shows the centre of Converse County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Converse County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem