SOLAR + STORAGE Β· MISO

Solar + storage project J3629, Bolivar County

Solar + storage project J3629, Bolivar County is a 210 MW solar + storage request withdrawn in the MISO interconnection queue, in Bolivar County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3629
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
DELTA SWYD - DREW [MS] 115.0kV
Location
Bolivar County, Mississippi
Technology
Solar: 210 MW Β· Battery
Total requested
210 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
December 2027
Withdrawn
September 2025

Location

Marker shows the centre of Bolivar County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Bolivar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem