Dundee Wind Increase

Dundee Wind Increase is a 3.9 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Penobscot County, Maine.

Queue statusOperating
  1. PlanningQueued May 2009 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
301
Grid region
ISO-NE (New England)
Connection point (POI)
BHE Keene Rd Substation
Location
Penobscot County, Maine
Technology
Wind: 3.9 MW
Total requested
3.9 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
28 May 2009
Proposed online date
July 2011

Location

Marker shows the centre of Penobscot County; the queue data does not give exact sites.