ONSHORE WIND · WEST

Invenergy Wind Development

Invenergy Wind Development is a 180 MW onshore wind request withdrawn in the West interconnection queue, in Morrow County, Oregon, connecting to Invenergy Wind Development LLC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G120
Grid region
West (non-ISO utilities)
Utility / transmission owner
Invenergy Wind Development LLC
Developer
Invenergy Wind Development LLC
Connection point (POI)
McNary – Santiam 230 kV transmission line
Location
Morrow County, Oregon
Technology
Wind: 180 MW
Total requested
180 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
24 November 2003
Proposed online date
December 2005

Location

Marker shows the centre of Morrow County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Morrow County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem