Solar + storage project 1200, Yakima County

Solar + storage project 1200, Yakima County is a 150 MW solar + storage request withdrawn in the West interconnection queue, in Yakima County, Washington, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1200
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Outlook substation
Location
Yakima County, Washington
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
Request assumed to be submitted to 2021 cluster
Queue status
Withdrawn
Entered queue
30 March 2020
Proposed online date
January 2023

Location

Marker shows the centre of Yakima County; the queue data does not give exact sites.