Solar + storage project AH1-639, Mahoning County

Solar + storage project AH1-639, Mahoning County is a 150 MW solar + storage request withdrawn in the PJM interconnection queue, in Mahoning County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-639
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Lordstown - Mansfield 345 kV
Location
Mahoning County, Ohio
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
13 September 2021
Proposed online date
October 2025
Withdrawn
December 2024

Location

Marker shows the centre of Mahoning County; the queue data does not give exact sites.