πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G226, Pipestone County

Onshore wind project G226, Pipestone County is a 9.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Pipestone County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedDec 2003 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G226
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Pipestone County, Minnesota
Technology
Wind: 9.0 MW
Total requested
9.0 MW
Study phase
IA Executed
Queue status
Withdrawn
Entered queue
30 July 2001
Agreement signed
2 December 2003
Proposed online date
May 2007

Location

Marker shows the centre of Pipestone County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Pipestone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem