πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project G0873, Walla Walla County

Onshore wind project G0873, Walla Walla County is a 300 MW onshore wind request withdrawn in the West interconnection queue, in Walla Walla County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0873
Grid region
West (non-ISO utilities)
Connection point (POI)
Lower Monumental Substation
Location
Walla Walla County, Washington
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
30 June 2023
Proposed online date
December 2029

Location

Marker shows the centre of Walla Walla County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Walla Walla County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem