United States › Grid › Interconnection queues › California

SOLAR · CAISO

Big Rock Suntower Generating Station

Big Rock Suntower Generating Station is a 33.0 MW solar request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2008 (completed)
  2. Withdrawn / abandonedMay 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
296
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Antelope-Piute 66kV line
Location
Los Angeles County, California
Technology
Solar: 33.0 MW
Total requested
33.0 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
18 January 2008
Proposed online date
December 2009
Withdrawn
May 2008

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County