United States βΊ Grid βΊ Interconnection queues βΊ Indiana
BATTERY STORAGE Β· PJMBattery storage project AG1-448, Laporte County
Battery storage project AG1-448, Laporte County is a 55.0 MW battery storage request withdrawn in the PJM interconnection queue, in Laporte County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedJan 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-448
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Olive-University Park 345 kV
- Location
- Laporte County, Indiana
- Technology
- Battery: 55.0 MW
- Total requested
- 55.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- December 2023
- Withdrawn
- January 2022
Location
Marker shows the centre of Laporte County; the queue data does not give exact sites.
Other requests in Laporte County
- Battery storage project J1355, Laporte CountyBattery storage Β· 160 MW Β· agreement signed
- Battery storage project J1358, Laporte CountyBattery storage Β· 125 MW Β· agreement signed
- Bluestem SolarSolar Β· 125 MW Β· agreement signed
- Solar + storage project AH2-419, Laporte CountySolar + storage Β· 210 MW Β· in study
- Solar project J1724, Laporte CountySolar Β· 150 MW Β· in study
- Solar project J3679, Laporte CountySolar Β· 149 MW Β· in study
- Solar + storage project AI1-080, Laporte CountySolar + storage Β· 125 MW Β· in study
- Bluestem SolarSolar Β· 125 MW Β· in study
- Solar project J2187, Laporte CountySolar Β· 124 MW Β· in study
- Solar project J1785, Laporte CountySolar Β· 100 MW Β· in study
- Bluestem SolarBattery storage Β· 55.0 MW Β· in study
- Battery storage project J1861, Laporte CountyBattery storage Β· 45.0 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem