HYDRO · CAISO

Mendocino Waveconnect Project

Mendocino Waveconnect Project is a 40.0 MW hydro request withdrawn in the CAISO interconnection queue, in Mendocino County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2007 (completed)
  2. Withdrawn / abandonedNov 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
280
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Fort Bragg Substation 60kV bus
Location
Mendocino County, California
Technology
Hydro: 40.0 MW
Total requested
40.0 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 November 2007
Proposed online date
June 2012
Withdrawn
November 2008

Location

Marker shows the centre of Mendocino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Mendocino County