SOLAR Β· SOUTHEASTSolar project IC-405, Dougherty County
Solar project IC-405, Dougherty County is a 29.4 MW solar request withdrawn in the Southeast interconnection queue, in Dougherty County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2015 (completed)
- Withdrawn / abandonedJul 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-405
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Albany - Mitchell (Black) 115 kV Line
- Location
- Dougherty County, Georgia
- Technology
- Solar: 29.4 MW
- Total requested
- 29.4 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 29 January 2015
- Withdrawn
- July 2015
Location
Marker shows the centre of Dougherty County; the queue data does not give exact sites.
Other requests in Dougherty County
- Solar + storage project 25-IC-1383, Dougherty CountySolar + storage Β· 199 MW Β· in study
- Dougherty County BESSBattery storage Β· 120 MW Β· in study
- Dougherty County SolarSolar Β· 120 MW Β· built
- Albany Green EnergyOther Β· 44.0 MW Β· built
- MCLB SolarSolar Β· 31.0 MW Β· built
- Solar project IC-472, Dougherty CountySolar Β· 200 MW Β· withdrawn