Battery storage project 25-IC-1325, Douglas County

Battery storage project 25-IC-1325, Douglas County is a 250 MW battery storage request withdrawn in the Southeast interconnection queue, in Douglas County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25-IC-1325
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Hickory Level - Yellow Dirt 230 kV Line
Location
Douglas County, Georgia
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
11 April 2025
Withdrawn
December 2025

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Douglas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem