Tesoro Refinery Cogeneration

Tesoro Refinery Cogeneration is a 104 MW gas request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2007 (completed)
  2. Withdrawn / abandonedNov 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
261
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Hinson Substation 220kV
Location
Los Angeles County, California
Technology
Gas: 104 MW
Total requested
104 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
28 September 2007
Proposed online date
October 2010
Withdrawn
November 2008

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County