United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

El Algodon Alto W

El Algodon Alto W is a 201 MW onshore wind request built and operating in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusOperating
  1. PlanningQueued Feb 2013 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (completed)
  4. OperatingMay 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
15INR0034
Grid region
ERCOT (Texas)
Developer
RWE Renewables Development, LLC
Connection point (POI)
tap 345kV 8455 Lon Hill -8606 Goddard
Location
San Patricio County, Texas
Technology
Wind: 201 MW
Total requested
201 MW
Study phase
IA
Queue status
Operational
Entered queue
3 February 2013
Agreement signed
2 April 2020
Proposed online date
April 2022
Came online
May 2022

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem