🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Jaguar BESS_1

Jaguar BESS_1 is a 157 MW solar + storage request built and operating in the ERCOT interconnection queue, in Mclennan County, Texas.

Queue statusOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0809
Grid region
ERCOT (Texas)
Developer
PP Jaguar BESS LLC
Connection point (POI)
Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch
Location
Mclennan County, Texas
Technology
Battery: 157 MW · Battery
Total requested
157 MW
Study phase
FIS & SS Incomplete
Queue status
Operational
Proposed online date
October 2025
Came online
December 2025

Location

Marker shows the centre of Mclennan County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mclennan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem