Onshore wind project 115, Columbia County

Onshore wind project 115, Columbia County is a 39.6 MW onshore wind request withdrawn in the West interconnection queue, in Columbia County, Washington, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
115
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Between Dayton and Pomeroy on the Dry Gulch-Mill Creek line
Location
Columbia County, Washington
Technology
Wind: 39.6 MW
Total requested
39.6 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
27 December 2006
Proposed online date
December 2008

Location

Marker shows the centre of Columbia County; the queue data does not give exact sites.