πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-153, Mcclain County

Onshore wind project GEN-2017-153, Mcclain County is a 253 MW onshore wind request withdrawn in the SPP interconnection queue, in Mcclain County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-153
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
McClain 138kV
Location
Mcclain County, Oklahoma
Technology
Wind: 253 MW
Total requested
253 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 November 2017
Proposed online date
December 2020
Withdrawn
September 2022

Location

Marker shows the centre of Mcclain County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Mcclain County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem