United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Aquilla Lake Wind

Aquilla Lake Wind is a 202 MW onshore wind request built and operating in the ERCOT interconnection queue, in Hill County, Texas.

Queue statusOperating
  1. PlanningQueued Jul 2018 (completed)
  2. ConsentedJun 2020 (completed)
  3. Construction (completed)
  4. OperatingJan 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0145
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
68090 Sam Switch 345 kV
Location
Hill County, Texas
Technology
Wind: 202 MW
Total requested
202 MW
Study phase
IA
Queue status
Operational
Entered queue
17 July 2018
Agreement signed
30 June 2020
Proposed online date
February 2023
Came online
January 2023

Location

Marker shows the centre of Hill County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hill County