ONSHORE WIND Β· ERCOT

Venado Wind

Venado Wind is a 202 MW onshore wind request built and operating in the ERCOT interconnection queue, in Starr County, Texas.

Queue statusOperating
  1. PlanningQueued May 2015 (completed)
  2. ConsentedDec 2018 (completed)
  3. Construction (completed)
  4. OperatingDec 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
16INR0111
Grid region
ERCOT (Texas)
Developer
Las Lomas Wind Energy, LLC
Connection point (POI)
8957 Lopeno 138kV
Location
Starr County, Texas
Technology
Wind: 202 MW
Total requested
202 MW
Study phase
IA
Queue status
Operational
Entered queue
17 May 2015
Agreement signed
22 December 2018
Proposed online date
December 2021
Came online
December 2021

Location

Marker shows the centre of Starr County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Starr County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem