United States βΊ Grid βΊ Interconnection queues βΊ Florida
SOLAR Β· SOUTHEASTSolar project 6
Solar project 6 is a 5.0 MW solar request withdrawn in the Southeast interconnection queue, connecting to Seminole Electric Cooperative.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2012 (completed)
- Withdrawn / abandonedMar 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 6
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Seminole Electric Cooperative
- Connection point (POI)
- Sorrento
- Location
- Florida
- Technology
- Solar: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: Feasibility; Status: Withdrawn by Customer on 3/18/2013
- Queue status
- Withdrawn
- Entered queue
- 25 April 2012
- Proposed online date
- December 2011
- Withdrawn
- March 2013
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem