United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

Bremen Solar

Bremen Solar is a 102 MW solar request withdrawn in the NYISO interconnection queue, in Lewis County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1302
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
New Bremen Solar
Connection point (POI)
Bremen 115 kV Substation
Location
Lewis County, New York
Technology
Solar: 102 MW
Total requested
102 MW
Queue status
Withdrawn
Entered queue
10 November 2021
Withdrawn
March 2022

Location

Marker shows the centre of Lewis County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Lewis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem