SOLAR Β· SOUTHEASTSolar project 303, Liberty County
Solar project 303, Liberty County is a 74.9 MW solar request withdrawn in the Southeast interconnection queue, in Liberty County, Florida, connecting to Duke Energy Florida.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 303
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Liberty Substation
- Location
- Liberty County, Florida
- Technology
- Solar: 74.9 MW
- Total requested
- 74.9 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 26 January 2022
- Proposed online date
- October 2023
Location
Marker shows the centre of Liberty County; the queue data does not give exact sites.
Other requests in Liberty County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem