SOLAR · SPPSolar project GEN-2015-021, Stanton County
Solar project GEN-2015-021, Stanton County is a 20.0 MW solar request built and operating in the SPP interconnection queue, in Stanton County, Kansas, connecting to SUNC.
Request details
- Queue ID
- GEN-2015-021
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Johnson Corner 115kV
- Location
- Stanton County, Kansas
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 1 April 2015
- Proposed online date
- April 2020
- Came online
- April 2020
Location
Marker shows the centre of Stanton County; the queue data does not give exact sites.
Other requests in Stanton County
- Onshore wind project GEN-2023-039, Stanton CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2023-068, Stanton CountyOnshore wind · 250 MW · withdrawn
- Solar project GEN-2017-052, Stanton CountySolar · 25.0 MW · withdrawn
- Solar project GEN-2014-071, Stanton CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem