Solar project GEN-2015-021, Stanton County

Solar project GEN-2015-021, Stanton County is a 20.0 MW solar request built and operating in the SPP interconnection queue, in Stanton County, Kansas, connecting to SUNC.

Queue statusOperating
  1. PlanningQueued Apr 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingApr 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-021
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Johnson Corner 115kV
Location
Stanton County, Kansas
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
1 April 2015
Proposed online date
April 2020
Came online
April 2020

Location

Marker shows the centre of Stanton County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Stanton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem