United States βΊ Grid βΊ Interconnection queues βΊ Kansas
SOLAR Β· SPPSolar project GEN-2017-052, Stanton County
Solar project GEN-2017-052, Stanton County is a 25.0 MW solar request withdrawn in the SPP interconnection queue, in Stanton County, Kansas, connecting to SUNC.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedMay 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-052
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Tap Bear Creek-Johnson Corner 115 kV
- Location
- Stanton County, Kansas
- Technology
- Solar: 25.0 MW
- Total requested
- 25.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 4 May 2017
- Proposed online date
- January 2019
- Withdrawn
- May 2021
Location
Marker shows the centre of Stanton County; the queue data does not give exact sites.
Other requests in Stanton County
- Solar project GEN-2015-021, Stanton CountySolar Β· 20.0 MW Β· built
- Onshore wind project GEN-2023-039, Stanton CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2023-068, Stanton CountyOnshore wind Β· 250 MW Β· withdrawn
- Solar project GEN-2014-071, Stanton CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem