United States › Grid › Interconnection queues › California

SOLAR · CAISO

Pearblossom Solar

Pearblossom Solar is a 9.5 MW solar request built and operating in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Apr 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1003A
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vincent Substation 230kV
Location
Los Angeles County, California
Technology
Solar: 9.5 MW
Total requested
9.5 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
30 April 2013
Proposed online date
October 2016
Came online
December 2016

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem